BGHS Construction Updates

Last Updated: 3/23/2021 5:07 PM

Demo of the Dome: March 2021

 

PHASE ONE: Completed August 2020

PHASE TWO: Farewell to the EL (El Donaldson Stadium, December 2020)

RENDERINGS OF FINAL PROJECT: Scheduled for Completion Fall 2023

 

TIMELINE:

SPRING 2021:

  • March 12: Fencing added to restrict access by the pool
  • March 15: Begin demolition of the Dome
  • April 3: Fence off access to the front of the Arena
  • SPRING BREAK: New doors installed at entrance to rear of the Arena
  • Mid-April: Begin foundation work for new classrooms and auditorium

SUMMER 2021:

Completion of BGHS Football Stadium & Track

DECEMBER 17, 2021:

Last day to occupy "Old" BGHS Building

JANUARY 2022:

  • Occupy new Culinary Arts, Child Development, and five standard classrooms on the 2nd Floor
  • Demolition begins for "Old" BGHS Building

FEBRUARY 2022:

Occupy new auditorium

DRAFT DESIGNS: Future Football Stadium and Natatorium (Opening Fall 2021)

Football Graphics DraftNatatorium Render

 

Virtual Reality Tour of School Spaces:

If viewing on a phone, click the links and move to see 360-degrees of each space. If viewing on a computer, use the mouse to click, drag, and move around and inside the space.

  • Click here to view outside the new Bowling Green High School.
  • Click here to view inside the BGHS Commons, to be completed by the 2022-2023 school year.
  • Click here to view inside a common hallway space, near teacher work spaces, hallways, and classrooms. (Most completed in phase one.)
     

Drone Footage of Construction Process:


Ross Tarrant Architects | Alliance Corporation